CJSC «Eurocement Group»
CJSC «Eurocement Group»: delivery of equipment for a cement plant under construction.
Within 6 months, more than 400 flights of general and oversized cargo were made. The cargo arrived at the port of Rostov-on-Don in 19 ship lots.
Features of the project:
transportation was carried out in the customs transit mode, a large volume of cargo transported, coordination of stevedoring works in the port, customs clearance, full organization of transportation.
- Specifications
Route | |
Place of loading | port of Rostov-on-Don |
Place of unloading | of the settlement. Podgorensky, Voronezh region |
Length of route | 470 km |
Cargo characteristics | |
Width | up to 6.8 m |
Height | up to 5.3 m |