PS «SHEPSY»
PS «Shepsi» delivery and rigging unloading of the transformer in the v. Shepsy.
Features of the project and transportation:
receiving a railway transporter at the railway station of Shepsi, moving along the railway track 60 m, turning 120 degrees, loading by rigging on a low-bed trailer, delivery to the PS «Shepsi», unloading on the foundation by rigging method in cramped conditions.- Specifications
Route | |
Place of loading | railway station Shepsi, Krasnodar region |
Place of unloading | of the PS «Shepsi» v. Shepsi, Krasnodar region |
Length of route | 30 km |
Cargo characteristics | |
Mass of the transformer unit | 96 t |